In the course of processing the research project ‘Thermoelectricity in Steel Industry – Basic
works’ (your order 0010-450/4522112310 dated 24.01.2022) it became apparent that not all
tasks (work packages) could be processed in the scheduled period from 01.03.2022 to
28.02.2023.
The status of the research work carried out and the additional research work still to be
carried out is shown in the table below. The research work to be continued is highlighted in
yellow. As an important step in failure analysis IR-Thermography was added as WP4
(highlighted in light blue in the table).
A detailed description of the research work performed in the period 01.03.2022 – 28.02.2023
will be given in a separate report (not attached in this offer). For a quick overview of all the
research work, the protocols of the regularly scheduled TE meetings are attached. The TE
meetings took place typically every two weeks.
At this point it should be mentioned that within the framework of the aforementioned research
work, supporting research work was also carried out in connection with the voest-internal
project of recovering radiant heat energy by means of the RGS thermagy module (see
attached protocols).
Status | Finished |
---|---|
Effective start/end date | 01.03.2023 → 29.02.2024 |
Fields of science
- 103020 Surface physics
- 103 Physics, Astronomy
- 210006 Nanotechnology
- 103021 Optics
JKU Focus areas
- Sustainable Development: Responsible Technologies and Management